Tuesday, February 23, 2010

Metrics for Managing Project Risk

I was in a bookstore over the weekend and saw of copy of Identifying and Managing Project Risk by Tom Kendrick from HP. The book was published last year but I know of his work on project risk metrics from an earlier whitepaper that really showed how to get a handle on measuring and managing project risks.

Here are some examples of predictive risk metrics which serve as a distant early warning system for project difficulties.

Project size/scale risk

  • Project duration (elapsed calendar time)
  • Total effort (sum of all activity effort estimates)
  • Total cost (budget at completion)
  • Size-based deliverable analysis (component counts, number of major deliverables, lines of non-commented code, blocks on system diagrams)
  • Staff size (full-time equivalent and/or total individuals)
  • Number of planned activities
  • Total length (sum of all activity durations if executed sequentially)
  • Logical length (maximum number of activities on a single network path)
  • Logical width (maximum number of parallel paths)

Schedule risk

  • Activity duration estimates compared with worst-case duration estimates
  • Number of critical (or near-critical) paths in project network
  • Logical project complexity (the ratio of activity dependencies to activities)
  • Maximum number of predecessors for any milestone
  • Total number of external predecessor dependencies
  • Project independence (ratio of internal dependencies to all dependencies)
  • Total float (sum of total project activity float)
  • Project density (ratio of total length to total length plus total float)

General risk

  • Number of identified risks
  • Quantitative (and qualitative) risk assessments (severity analysis)
  • Adjusted total effort (project appraisal: comparing baseline plan with completed similar projects, adjusting for significant differences)
  • Survey-based risk assessment (summarized risk data collected from
    project staff, using selected assessment questions)
  • Aggregated overall schedule risk (or aggregated worst-case duration estimates)
  • Aggregated resource risk (or aggregated worst-case cost estimates)

And the last example, the Dilbert Correlation Factor: collect 30 recent Dilbert cartoons and circulate to staff. Have people mark each one that reminds them of your organization. If the team average is

  • under 10: Low organization risk.
  • 10-20: Time for some process improvement.
  • Over 20: Hire a cartoonist and make your fortune….)

3 comments:

boy labyog said...

Thanks for sharing your wonderful idea i much appreciate it.




Laby[dress pants]

Andrew Rayy said...
This comment has been removed by the author.
Andrew Rayy said...

Wonderful article! This provided detailed information about project management and how to make use of it. Moreover, I have seen a growing demand for Project management certified professionals. With the help of training providers like http://www.pmstudy.com , I was able to prepare for my PMP exam in an efficient manner.The PMP Certification